Article - CS98146
Integrity Lifecycle Manager MS Project integration: Use standardized date field format on synchronization with Integrity
Modified: 05-Dec-2016
Applies To
- PTC RV&S (formerly Integrity Lifecycle Manager) 2007 2007 SP6 to 10.8
- Applies to Integrity MS Project Integration versions prior 1.6
- MS Project 2003, 2007, 2010 and 2013 (as of integration version 1.4)
Description
- Use standardized format for date fields to be synchronized with Integrity
- Date fields will not be correctly synchronized, when date format in MS Project does not match the format specified in mapping template for Integrity Lifecycle Manager