User becomes the status manager after using Microsoft Project Professional to load a project schedule into a Microsoft Project Server project that is associated with a Windchill PPMLink 10.1 site

Modified: 06-Sep-2012   


Applies To

  • Windchill PPMLink 10.1
  • Microsoft Project Professional 2002, 2003, 2007, and 2010

Description

  • You can use the Import Project to Enterprise or Save As actions in Microsoft Project Professional to load a project schedule into a Microsoft Project Server Project that is associated with a Windchill PPMLink site.
  • Once the project is published, the user who performed the action becomes the status manager of all tasks in the project.
  • The status manager has privileges similar to the project owner.