"Process Plan" or "WTPart" is not checked out when they are associated/linked with each other in Windchill MPMLink
Modified: 12-Nov-2024
Applies To
- Windchill PDMLink 10.1 to 13.0
- Windchill MPMLink 10.1 to 13.0
Description
- Process Plan or WTPart is not checked out when they are associated/linked with each other
- Why no need to check out process plan to link part or vice-versa
- Why not check out process plan to link part
- Does not need to checkout part to link process plan. Why ?
- User with no modify access to WTPart can associate process plan
- When adding a WTPart as a Related Part to a Process Plan, neither the Part nor the Process Plan are checked out and remain in same Iteration