Article - CS413469
When a project is created with automatic execution control the activities are not triggering automatically in Windchill ProjectLink
Modified: 06-Jan-2025
Applies To
- Windchill ProjectLink 12.1.0.0 to 12.1.2.10
- Windchill ProjectLink 13.0.0.0 to 13.0.1.4
Description
- Once predecessor activity completes, successor Activity Starts only when the Estimated Finish time is passed for Automatic Execution of Project
- The task has reached the start time, the Summary Activity status is Processing, but the child activities are still Scheduled
- We have created a template for the plan, but in some cases, the plan activity predecessors are not being processed as expected.