Article - CS371737

Re-import of exported MS Plan failed with an error "Resource assignments on summary tasks are not supported" in Windchill PDMLink

Modified: 23-Jun-2022   


Applies To

  • Windchill ProjectLink 11.2

Description

  • Re-import of exported MS Plan failed with an error "Resource assignments on summary tasks are not supported"
  • Error in the Windchill UI after trying to import an exported MS Plan:
    • User-added image
  • When trying to import the Plan from the XML file, the following error is shown:
    • The Value for attribute Activity Status must be one of the following:
      NotStarted, OnGoing, Completed, Cancelled, Tailoredout.
      The pre-existing value may no longer be valid for this attribute.
      
    • User-added image