When editing child activity's duration, MFO of successor is not obeyed in Windchill ProjectLink
Applies To
- Windchill ProjectLink 11.1 to 12.0.0.1
Description
- When editing child activity's duration, MFO of successor is not obeyed in Windchill ProjectLink
Steps to Reproduce
- Create a Project
- Create a Plan
- Create Activities as below
- A1 - duration 5 - ASAP
- A2 - duration 2 - ASAP - add predecessor id of A1
- A3 - duration 1 - ASAP - add predecessor id of A2
- Now edit A3
- Change the constraint to MFO
- Create child activity A1-Child to A1 - duration 1 - ASAP
- Edit A1-Child and change duration to 300 days
- Click on finish, it gives popup , click on okay and again click on Finish
Expected: It should not accept duration as 300 days
Actual: It accepts 300 days and plan dates become invalid