Retrieval of first iteration NX Assembly data doesn't honor NX Load options instead component retrieval happens with load option as Fully Loaded in Windchill PDMlink Server configured with security labels

Modified: 09-Jun-2020   


Applies To

  • Windchill ProjectLink 12.0.0.0
  • Windchill PDMLink 12.0.0.0
  • Windchill Workgroup Manager 12.0.0.0
  • Siemens NX

Description

  • Opening of NX assembly doesn't honor Partially Load option instead retrieval happens as Fully Loaded for its components 
  • Component of NX Assembly loads with Fully loaded status when Assembly is open in NX with Partial load option, refer to below steps
    1. Checkin NX assembly having few components  to Windchill PDMLink
    2. Post checkin , perform  Remove from Workspace to remove  NX assembly and its dependent from workspace
    3. Add NX assembly and its dependent  to workspace and Open the Assembly with Partially Load option
    4. Notice the Component Properties for any components , those are loaded as Fully Loaded