Article - CS282092
If a workflow block (Sub-process) is completed manually using Complete Process action from Process Manager of Parent Process the Workflow Block shows Terminated in Windchill PDMLink
Modified: 22-Mar-2018
Applies To
- Windchill PDMLink 11.0
Description
- If a workflow block (Sub-process) is completed manually using Complete Process action from Process Manager of Parent Process the Workflow Block shows Terminated
- Completing a Workflow Block from Process Manager using Complete Process action(button) shows the activity terminated and workflow is in Executed state