Article - CS25115

Activity precedence rules not obeyed if project execution is controlled manually in Windchill ProjectLink

Modified: 18-Sep-2025   


Applies To

  • Windchill PDMLink 9.1 to 13.0

Description

  • Activity precedence rules not obeyed if project execution is controlled manually
  • Activities are not assigned according to the rules of their predecessors
  • Successor activity can be completed manually before the predecessor activity is complete even though the Finish-to-Start precedence rule is set
This is a printer-friendly version of Article 25115 and may be out of date. For the latest version click CS25115