Article - CS250656

Whenever percent work complete of an activity is updated, does it get rolled up to the plan in Windchill ProjectLink

Modified: 31-Jul-2025   


Applies To

  • Windchill ProjectLink 10.0 to 13.1

Description

  • Whenever percent work complete of an activity is updated, does it get rolled up to the Project Plan
  • Sometimes after updating work complete percentage of an activity, the Project Plan work complete percentage is changed
  • Sometimes after updating work complete percentage of an activity, the Project Plan work complete percentage is not changed
  • What is the calculation mechanism for Project Plan work complete percentage
  • "% Work Complete" field does not reflect the status of completed child tasks in a Project plan
  • Parent task "% Work Complete" remains unchanged despite updates to child tasks