Article - CS220326
It doesn't take care of the hours and minutes mentioned in deadline tab while assigning workflow task if the deadline consists of days, hours and minutes in Windchill PDMLink 10.1 system
Modified: 19-Nov-2015
Applies To
- Windchill PDMLink 10.1 to 11.1
Description
- In Site>Utilities>Calendar Management page mark 2015/10/1 as non-working day

- Go to Site>Utilities>Workflow Template Administration and open Process 1 workflow template to set 4 hours in Deadline tab page for the activity.

- Start workflow in 2015/10/1 and user can’t see the 4 hours difference between Assigned time and Deadline time.