Article - CS217086

Workflow tasks are assigned to the Creator instead of the Role defined in the workflow in Windchill ProjectLink

Modified: 17-Jul-2018   


Applies To

  • Windchill ProjectLink 9.0 to 11.2

Description

  • Workflow tasks are assigned to the Creator instead of the Role defined in the workflow
  • The expected Roles are populated in the Members table on the Process tab for the primary business object, but there are no users populated in those roles
  • In a Product context, the assignment works as expected, assigning the tasks to the Role defined in the Workflow and the Team Template