Article - CS201345
TrackWork and Complete don't have the same behavior on the project Status icon in Windchill PDMLink 10.2 M020
Modified: 14-Aug-2017
Applies To
- Windchill 10.2 all datecodes
Description
- In ProjectLink, When you complete a project assignment (RMB -> Work Track -> 100% ), the project Status is "green". However when you complete a project assignment (RMB -> Complete), the project Status is "?"
- When setting the Trackwork to 100%, the project status goes green whereas the project status show "?" if you use the Complete action.
This is a printer-friendly version of Article 201345 and may be out of date. For the latest version click CS201345