How to enable "Mark Working" and "Mark Nonworking" on the system or individual user calendars in Windchill PDMLink

Modified: 03-Aug-2025   


Applies To

  • Windchill PDMLink 9.1 to 13.0
  • FlexPLM 11.0 to 11.1

Description

  • Neither Mark Working nor Mark Nonworking works on any date in calendar
  • How to enable Mark Working and Mark Nonworking on system or individual user calendars?
  • How to set other non working days than Saturday and Sunday
  • How to set the working / non working day in system calendar
  • How to define working days
  • Calendar tasks start and end date does not consider weekends
  • When an activity was created in a non-working day, how deadline was set ?
  • Why deadline is shown as next Tuesday when an activity was created on Saturday.
  • Why system calendar do not set Saturday and Sunday to defaut nonworking date? 
  • Holidays/Sundays exemption while applying the Task dead lines to Windchill Workflow activity
  • How can I define my own weekend days
  • How to apply Public After setting wt.calendar.nonWorkDaysOfTheWeek=1
  • Set the deadline for a workflow task to complete automatically, it cannot be finish if the deadline was a Non-Working day