How to enable "Mark Working" and "Mark Nonworking" on the system or individual user calendars in Windchill PDMLink
Modified: 03-Aug-2025
Applies To
- Windchill PDMLink 9.1 to 13.0
- FlexPLM 11.0 to 11.1
Description
- Neither Mark Working nor Mark Nonworking works on any date in calendar
- How to enable Mark Working and Mark Nonworking on system or individual user calendars?
- How to set other non working days than Saturday and Sunday
- How to set the working / non working day in system calendar
- How to define working days
- Calendar tasks start and end date does not consider weekends
- When an activity was created in a non-working day, how deadline was set ?
- Why deadline is shown as next Tuesday when an activity was created on Saturday.
- Why system calendar do not set Saturday and Sunday to defaut nonworking date?
- Holidays/Sundays exemption while applying the Task dead lines to Windchill Workflow activity
- How can I define my own weekend days
- How to apply Public After setting wt.calendar.nonWorkDaysOfTheWeek=1
- Set the deadline for a workflow task to complete automatically, it cannot be finish if the deadline was a Non-Working day