Article - CS157092
When a Project Milestone with a linked Deliverable is completed to 100%, Milestone status shows Question mark and Checkmark i.e. 'Unavailable Completed' instead of 'Green Completed' in Windchill ProjectLink 10.1
Modified: 04-Jan-2016
Applies To
- Windchill PDMLink 10.0 to 10.2
Description
When a Project Milestone with a linked Deliverable is completed to 100%, Milestone status shows Question mark and Checkmark i.e. 'Unavailable Completed' instead of 'Green Completed'


This is a printer-friendly version of Article 157092 and may be out of date. For the latest version click CS157092