Article - CS343270
In Windchill MPMLink, cannot check out an operation with error "Process Plan - xxx can not be checked out because it is not the latest iteration."
Modified: 13-May-2024
Applies To
- Windchill MPMLink 11.0 M030 to 13.0
- Preference Automatic Check Out Process Plan is set to Yes
- The operation was draged to deeper level, such as from second level to third level
Description
- Cannot check out an operation with below error
Process Plan - xxx can not be checked out because it is not the latest iteration.
- When more than one person edits an operation in the process plan at the same time, it prompts:
The system is not able to check out the parent process plan. Ensure that you can modify the parent process plan before proceeding.