In Windchill MPMLink, cannot check out an operation with error "Process Plan - xxx can not be checked out because it is not the latest iteration."

Modified: 13-May-2024   


Applies To

  • Windchill MPMLink 11.0 M030 to 13.0
  • Preference Automatic Check Out Process Plan is set to Yes
  • The operation was draged to deeper level, such as from second level to third level

Description

  • Cannot check out an operation with below error
    Process Plan - xxx can not be checked out because it is not the latest iteration.
  • When more than one person edits an operation in the process plan at the same time, it prompts:
The system is not able to check out the parent process plan. Ensure that you can modify the parent process plan before proceeding.