When running a High Availability Identical Node Cluster, attempting to configure multiple, simultaneous SolidWorks workers on the same machine fails. What options are available to service multiple cluster nodes?

Modified: 18-Nov-2016   


Applies To

  • Creo View Adapters 3.0 to 4.2
  • Windchill PDMLink 10.2 to 11.1
  • Windchill ProjectLink 10.2 to 11.1
  • Windchill PDM Essentials 10.2 to 11.1
  • SolidWorks

Description

  • A High Availability Identical Node Cluster is configured to run multiple, simultaneous SolidWorks workers on the same worker machine, for example:
    • Cluster node1 is configured with worker machine1 SolidWorks worker1
    • Cluster node2 is configured with worker machine1 SolidWorks worker2
    • Cluster node3 is configured with worker machine1 SolidWorks worker3
  • Startup of a second or third worker always fails if a SolidWorks worker is already running
  • What worker or cluster configuration options are available to service multiple cluster nodes?